Midstream: Bakken outage
Bakken producers truck crude to Dakota Access as Enbridge's North Dakota line stays curtailed
A week into reduced flows on a 475,000 b/d pipeline, some barrels are moving by road, at least two Midwest refiners have declared force majeure and Enbridge has given no restart date.
Enbridge's North Dakota Pipeline has run at lower rates since last week, after reports of tainted crude led the company to test for organic chlorides, Bloomberg reported on Friday. Enbridge has not given a timeline for restoring normal flows on the 475,000 b/d system, Reuters reported earlier in the week.
Some producers and marketers are now trucking barrels to delivery points on the Dakota Access Pipeline, according to Energy Aspects analyst Jeremy Irwin, who said at least two Midwest refiners have declared force majeure on Bakken deliveries. A Reuters source named Flint Hills Resources' Pine Bend refinery in Minnesota as one, and Marathon Petroleum's MPLX unit declared force majeure on North Dakota deliveries on November 18. Energy Aspects expects the loss to tighten Midcontinent light sweet supply.
Bloomberg said the disruption could draw down crude stocks at Cushing, Oklahoma. The wider market is soft: December WTI settled at $83.98 on Friday, up 77 cents but down about 5% on the week, its third weekly drop, as tanker traffic through Hormuz returned to near prewar levels, Reuters reported.
Sources: Bloomberg via Insurance Journal; Reuters via BOE Report; Seeking Alpha; Reuters via Investing.com